Font: IncreaseFont: NormalFont: Decrease
 
 
The Official Website of
Sarawak Timber Industry Development Corporation
 
 
 

STIDC strives to provide a safe and conducive working environment for its tenants at Wisma Sumber Alam. Following this, listed below are the approved projects, which has been scheduled to be implemented in November 2020 till July 2022. These projects will be under the supervision of Building Management Section.

BIL PROJECT START COMPLETED
1

The Supply, Delivery, Installation, Testing & Commissioning of Centralized Air-Conditioning System (Phase-1) at Tower Block, Wisma Sumber Alam, Kuching, Sarawak.

November 2020 Februari 2022
2

The Proposed New External Facade Treatment and The Refurbishment of Main Entrance Drop-Off Lobby to Wisma Sumber Alam.

Januari 2021 Julai 2022
3

The Proposed Upgrading and Improvement of Existing Six (6) Units of Lift at Wisma Sumber Alam at Tower Block, Kuching, Sarawak.

April 2021 Jun 2022